"Construction practice may vary in different places or geography, as such, these notes are just general information" . In time, new photos will be added.
DEVELOPMENT, TENDER, AND CONSTRUCTION SEQUENCE
Ownership
Land matters
Survey
Layout:
Submission
Infra:
Submission-JPP, JBA, TNB, Telekom, JKR, Masma,
Road&Drainage
Submission carried out by Civil Engineer
Earthwork:
Submission
Earthwork
Submission carried out by Civil Engineer
Setting out:
Survey and setting out plan
Survey to be carried out by Chartered Surveyor, pegging
shall be installed, after which Main Contractor upon taking site possession
shall verify the pegging layout with their own certified surveyor. Pegs shall
be protected by Main Contractor.
Planning:
Submission
Planning submission (for Building) to be carried out by
Architect. Planning guidelines shall be complied.
Fire Fighting
Submission to JBPM shall be done by Architect. Bomba
guideline shall be complied.
Building:
Submission
Building submission shall be done by Architect. Building
guidelines/ by-laws shall be complied.
Landscape:
Submission
Landscape submission shall be done by Landscape Architect.
Tender:
Preparation of tender
Design proposal confirmed by the Client shall be prepared in
working drawing sets, which will be produced as Tender drawings, Submission
drawings, and Construction drawings. Tender document in parts, consist of Bill of
Quantity, Preliminaries, Preamble, Condition of Tender, Instruction to
Tenderer, Specifications, Schedule of Finishes, Schedule of Rates, etc.
Calling of tender
Tenderers are expected to have visited the site before
submitting the quotation.
Tender clarification
Selected tenderers who return tender shall be called for
tender clarification, to finalize any query before revise quotation.
Award
Selected Contractor shall be issued with Letter of Award
describing the condition of the contract.
Site Possession/Commencement:
Mobilization
Upon possession of site, and acceptance of the site
condition, the Main Contractor shall start mobilizing equipment, material,
workers etc to the site.
Acceptance of site condition
Main Contractor shall write in their acceptance of existing
site condition, mentioning that the condition of the site, the site and work
access, and no obstruction to the intended works.
Submission of Performance Bond, CAR, WC shall be done by
Main Contractor immediately.
Notice that site setting out peggings are protected with
timber studs. The pegs shall remains protected until preparation of formwork of
the affected area. The difficulties are in keeping pegs in place while the site
is run by heavy machinery and excavation starts.
Verification of survey:
Setting out
Survey to be carried out by Chartered Surveyor, pegging
shall be installed, after which Main Contractor upon taking site possession
shall verify the pegging layout with their own certified surveyor. Pegs shall
be protected by Main Contractor.
OGL
Main Contractor shall survey the original ground levels, to
determine the quantity of additional or omission of earth required.
Upon possession of site, the contractor shall prepare the site on security, safety and cleanliness. Notice that the earth drain is created to discharge surface water from the site.
Coordination:
Drawings/shopdrawings
Main Contractor shall, in reference to Consultants’
construction drawings, prepare coordination drawings, covering all detail
dimensions, construction method, sequence of works, etc.. Shop drawing shall be
prepared by Main contractor immediately according to required timing and
sequence of work.
Site
Descrepencies
Sequence of works
Test:
Soil
Pile
Concrete
Foundation:
Coordination of site before excavation
Excavation
Excavation work requires proper coordination, so as not to
damage the block peggings, excavated earth not to obstruct the next works, and
the retained water to be pumped out.
Piling
Piling work in progress, which design derived from soil
test. Above are concrete. For the marine clay of the site, bakau piling could be specified.
As built
Formworks
Reinforced bar
Pile cap
After submission of piling point as built is accepted,
the preparation of formwork and installation of reinforcing bars starts.
Stump
Formwork removed, and the workers are preparing for
backfilling work and installation for formwork of stump: notice the starter
bars above pile caps.
Backfilling
Backfilling work completed, and the site is being prepared
for installation of formwork for stumps
and ground beams.
Sample/Material
Gutter/Rwdp
Windows/glazing
Sliding doors
Roof tiles/materials
Wall/floor tile
Brick (clay/cement sand)
Sanitary piping/fitting
Cold water piping/fitting
M&E pipe/cable/trunking/ducting
Colour scheme code/board
Ironmongery/lockset
Textured concrete/imprint
Water tank
Fan hook
Main Building work:
Superstructure/ substructure
After completion of substructure works, ground beam
formwork and casting are in progress.
R C frame work
BRC laying and formwork for 1st floor rc slab are in
progress.
Formworks for 1st floor columns are erected. Notice starter bars at the edge of
floor slab and column, which are meant for brickwall’s rebars.
1st floor beam and carporch beam formworks are
in progress.
Rc framework completed up to 1st floor and
formworks are dismantled. At this point of construction, installation of
architectural works /elements starts e.g.brickwall, rainwater down pipe in
columns, covered M&E pipings and conduits etc. Notice that external
sanitary manhole is completed, pending backfilling. Notice also orange colour
upvc pipes for dicharge of rainwater ( down pipe) have been laid pending connection to external
drain and backfilling.
Underground services:
Sanitary
Cold water
TNB
Telekom
As built
Above ground rc works
Formworks
Reinforced bar
Ground beam
Ground slab
Concealled services
Ground flr column
1st flr beam/slab
Concealled services
1st flr column
Roof beam
Preparation for roof beam formworks. Notice that metal
door frames are delivered to the site, ready for installation.
Rc framework is completed. Bricklaying and window frames
installation are in progress
Brickwalls completed with aluminum window frames in
place. Scaffoldings are erected in
preparation for plastering work. Notice that the rainwater down pipes are in
place to receive the pipes from gutter.
Plastering work is completing, and fabrication of roof
trusses commences.
Water tank support
Architectural works
Water tank
Roof trusses
Roof covering
Wall
Windows/Frame
Upper roof covering completed. Lower roof trusses of some
units are yet to be installed, pending dismantling of scaffoldings.
Glazing
Doors/Frame
Wall finishes
Wall plastering
Floor finishes
Ceiling
Painting
Painting work commences
As built
Rectification Method Statement
Works not according to Construction Dwg.
Incomplete works
Defects
Infra Works
Road & Drainage
Drain base work in progress.
Drain wall completed, notice the timber props are
installed to support the drain wall against the horizontal load of the
surrounding earth, until completely cured.
Pipe culvert laying in progress.
Drain cover completed.
Sewerage reticulation
Water reticulation
External Work
TNB
TNB sub station is in progress
Streetlighting
Telecom
Inspections
Consultants
Authority
During preparation and completion of painting and roof
works, series of joint site inspections are carried out by consultants and
developers, to identify incomplete, improper, or wrongly constructed works.
Notice that timber studs used to protect setting out pegs are still remain.
Formwork for drain wall is in progress. Once road and
drainage works commences, no heavy machineries should enter the unit’s
parameter, so as not to damage on going work.
Painting and lower roof works are in progress. Drain wall
rc work is completed pending backfilling.
TNB sub station’s fencing work is in progress.
TNB sub station is completed according to TNB’s
specifications.
Preparation of formwork for gate and fencing post.
Completed Semi D units, pending completion of infra work.
Notice that 1st layer crusher run for the road is in progress.
1st layer of crusher run, road kerb, and fire
hydrant are in place.
Binding course and wearing course for road are completed.
Landscape work and infra works completed, pending clearing and cleaning up for
Authority inspection.
May be appropriate to see a public/general guideline to a 'good construction practice' for contractor to follow.
ReplyDeleteCurrently, the fact is lost along the way , giving way to acceptable contract sum!!!...